State Bar of Texas Administrative and Public Law Section

Featured Article - November 1998

TEJAS LITIGATION:
HOW TO SUE THE STATE AND WIN UNDER A PRIVATIZATION CONTRACT

J. Stephen Ravel
Bickerstaff, Heath, Smiley, Pollan, Kever & McDaniel, L.L.P.

816 Congress, Suite 1700
Austin, Texas 78701

Roy Q. Minton
Minton, Burton, Foster & Collins,

A Professional Corporation
1100 Guadalupe Street
Austin, Texas 78701

© 1998 J. Stephen Ravel and Roy Q. Minton

presented at the

10th Annual Advanced Administrative Law Course
September 24-25, 1998
Austin, Texas

TABLE OF CONTENTS

  1. PROBLEM EVALUATION AND THE PASSAGE OF S.B. 19
  2. S.B. 178 AND THE LONG MARCH TO TRIAL
  3. THE REMOVAL TO FEDERAL COURT, ELEVENTH AMENDMENT IMMUNITY, AND THE FEDERAL CLAIMS FOR AN INJUNCTION
  4. THE STATE COURT TRIAL AND JUDGMENT
  5. CONCLUSION
  6. FOOTNOTES


Tejas Litigation: How to Sue the State and Win Under a Privatization Contract

Consider this Christmas Eve 1994 -- Initial Client Interview.(1)

My name is Bob Miller. I am the President of both Systems Control, Inc. ("SCI") and its 90% owned subsidiaries Tejas Testing Technology One and Tejas Testing Technology Two, L.C. ("Tejas") With me are Brad Laughlin and Darrell David, Vice Presidents of the Tejas entities and Project Managers in Tejas' Dallas and Houston operations respectively. Their company, Laughlin/David Partnership, owns 10% of each Tejas company. In the Spring of last year (1993), the two Tejas companies were the successful bidder for a major government contract with the Texas Natural Resource Conservation Commission's ("TNRCC") predecessor, the Texas Air Control Board. Tejas, whose bid was rated highest for quality and lowest for cost, won the right to provide federally mandated emissions tests to every car and truck in the Dallas/Fort Worth Metroplex and the Houston/Galveston/Beaumont/Port Arthur area for a term of seven years. The Program is authorized by and grounded in federal statute and regulation, as well as state statute and regulation. Tejas' sales volume is absolutely guaranteed. No car in those two areas can receive a renewal license tag without coming to a Tejas facility and submitting to and passing a roughly $20.00 test. The system we contracted to build and run is what is known as a "centralized" system. Testing cars is our only business. Car dealers and repair shops are not allowed to test cars in a centralized program. The EPA prefers centralized systems. In reliance on this very predicable revenue stream, the Tejas entities obtained over $100 million in financing to build and equip 65 high-tech emissions testing locations in the two metropolitan areas. All locations came on line to the TNRCC's satisfaction two weeks ago, ahead of schedule. At the TNRCC's request, we also opened to the public ahead of schedule. We have hired subcontractors (known as Operating Contractors)to actually operate the locations for us. Tejas and the Operating Contractors have trained over 2,000 employees. We have fully performed our construction phase obligations under the contract, and the State does not dispute that. Official testing begins on January 2, 1995. Trial period testing has gone great, and the TNRCC is effusive in their praise of our documented, full performance. We have done the hard part, and it is now time to efficiently run these 65 locations, to retire our debt, and to enjoy the fruits of our contract. SCI's management (along with others) bought the company in a leveraged buy-out last summer, adding over $20 million to our debt load. Total debt at all company levels now exceeds $120 million.

Since the November 1994 Congressional elections, we have been concerned that support for centralized emissions testing may be waning. We have just picked up a rumor that the TNRCC is studying unilateral cancellation of our program, but may wait for legislative input in that regard. Obviously, having our car volume and our revenue stream drop in any material way will be devastating to our business. What can you do to help us?

Thus began a 38-month odyssey with the greatest clients, co-counsel, and support staff imaginable.

I. PROBLEM EVALUATION AND THE PASSAGE OF S.B. 19

When Mr. Miller, Mr. Laughlin, and Mr. David came to see us, there was a classic conflict among the courts of appeal concerning "contractual" sovereign immunity. All courts agreed that the mere entry into a contract by the State with a private citizen waived immunity from LIABILITY. However, the courts of appeal were sharply divided on whether the mere entry into a contract waived immunity from SUIT. Some cases held that when the State contracts with a private citizen, it waived immunity from liability but retained immunity from suit, absent either a general or a specialized legislative enactment waiving liability from suit. More specifically, the Houston First Court, the Austin Court, the Fort Worth Court, the Houston 14th Court, the El Paso Court, and the Corpus Christi Court had written opinions indicating that absent a legislative enactment waiving immunity from suit, the plaintiff government contractor could not even get into court.(2) However, other cases had held that the State waived its immunity even from suit whenever it contracted with private citizens. Such opinions had come from the Dallas Court, the El Paso Court, and the Austin Court.(3) Notice that El Paso and Austin were represented in both camps. Given the large sums of money involved, we planned conservatively from the outset and assumed that rule of law then most recently stated in Green International, Inc. v. State, 877 S.W.2d 428, 432-433 (Tex. App. --- Austin, 1994 writ ultimately dism'd by agreement) would obtain and that we would have any breach of contract claim dismissed by a Travis County District Court absent a legislative enactment authorizing suit and/or some other plausible sovereign immunity waiver argument. Before 1994 was over, we found three legislative enactments that we believed amounted to a legislative authorization of suit. They were Texas Health & Safety Code § 382.032 and Texas Water Code §§ 5.351 and 5.352. These statutes specifically authorized a party aggrieved by an action of the TNRCC to file suit within 30 days in a District Court of Travis County challenging such aggrieving actions. While not employing actual sue or be sued language, we always believed that these statutes would be sufficient, even if the Texas Supreme Court adopted the view expressed in the more restrictive line of courts of appeal cases. We further satisfied ourselves that if our clients' contract rights were taken or impaired unconstitutionally, sovereign immunity would not be a bar to a claim for substantial money damages.

Having satisfied ourselves that we could probably obtain a contract-based judgment for our client employing both contract and constitutionally based theories, we next considered what mechanisms would be available to collect that judgment. Our research regarding collecting State judgments over the objection of a non-appropriating Texas Legislature was both surprising and disappointing. At that time, a very large whistle blower judgment in favor of George Green had gone unpaid for at least one full legislative session after becoming final. The Texas Supreme Court had summarily denied Green's Motion for Leave to File Writ of Mandamus seeking to compel Comptroller Sharp to pay the final judgment. See Green v. Sharp, 37 Tex. Sup. Ct. J. 1227 (Sept. 29, 1994). In a footnote in Texas Education Agency v. Leeper, 893 S.W.2d 432, 448, Justice Gonzalez described a rule of law in which a prevailing plaintiff must always "request a legislative appropriation to collect damages awarded him ...." Uncertainty concerning whether and by what procedure the State Comptroller could be mandated to pay an unsatisfied final judgment against the State arising from a contractual obligation remained unsettled throughout the pendency of the Tejas case and remains unsettled today.

Mandating payment from the State Treasuer appeared to be a better developed concept when a federal court judgment was involved. Two Fifth Circuit cases and one Ninth Circuit case actually described situations in which a federal judge compelled state fiscal officers by mandamus to pay civil rights judgments. In Gates v. Collier, 616 F.2d 1268 (5th Cir. 1980), modified on other grounds, 636 F.2d 942 (5th Cir. 1981), the Fifth Circuit affirmed a Mississippi District Court order the Fifth Circuit described as follows: "[The] Order directs that Mississippi's Auditor and Treasurer be added as defendants and that the other defendants submit a requisition to the Auditor for the issuance of a warrant upon the Treasurer to satisfy the judgment out of funds appropriated for the operation of Parchman [prison] or out of any other funds subject to control of the Treasurer." 616 F.2d at 1270. A Mississippi statute on the books at the time prohibited the satisfaction of judgments against the State except by legislative appropriation. The Fifth Circuit in Gates ruled, notwithstanding the Mississippi statute, that the trial court entered an appropriate order. At the time we were evaluating our clients' posture, the Fifth Circuit, the Seventh Circuit, and the Ninth Circuits had all followed Gates.

Probably by Ground Hogs Day 1995 and certainly by Valentine's Day 1995,(4) we knew that should our clients' contract be breached, or its contract rights be legislatively taken or impaired, we had a good chance of getting into court in the state system, could not point to well established collection methods for a state court judgment, felt surviving the immunity hurdle in federal court was more difficult, but collection of a federal judgment would be based on more established precedent.

On January 31, 1995, Governor George W. Bush signed his first bill into law. The legislation, Tex. S.B. 19, suspended the State's centralized vehicle emissions testing program for 90 days and funded an $8.8 million loan to the Tejas companies to compensate Tejas for its 90 days of lost revenue. The $8.8 million loan was a last minute, floor addition to the legislation. Earlier versions of the statute simply shut down the program and destroyed Tejas' revenue stream for 90 days, without any compensation whatsoever. The business deal behind the $8.8 million loan fully contemplated that centralized emissions testing would be resumed after 90 days. Senate Bill 19 made sense for the Tejas companies only if cars that were not tested during February, March, and April 1995 were required to be tested by the end of the 1995 to the 1997 state biennial budget period. Such was specifically discussed, and Tejas had high hopes that centralized testing would restart three months later in a slightly scaled down fashion. In response to earlier versions of the bill that did not provide for any sort of compensation, we prepared a breach of contract, impairment of contract, and takings original petition and request for temporary restraining order. Filing such did not become necessary because the $8.8 million "tide over" was added at the last minute. From February through April 1995, various emissions testing bills were filed and began to work their way through the legislative committee system. Tejas remained confident that while some of its legislatively contracted for monopoly might be lost, its program would continue in substantially similar form and any slight losses would be compensated. On May 1, 1995, the full weight of the Tejas State Capitol was dropped on the Tejas companies in the form of Tex. S.B. 178.

II. S.B. 178 AND THE LONG MARCH TO TRIAL

Texas Senate Bill 178 (among many other anti-Tejas provisions) expressly made ILLEGAL the very technology that Tejas had contracted to provide and accelerated the due date of Tejas' $8.8 million loan from August 31, 1997 to September 1, 1995. With one stroke of a pen, the commercial demand for Tejas' testing network and business disappeared. Prior to the passage of S.B. 178, one could not operate a car or light truck in the Metroplex or in Houston, Galveston, Beaumont, or Port Arthur without paying for a Tejas test every other year. Once S.B. 178 passed, no one needed a Tejas administered test and, therefore, nobody sought out such tests. There was no demand for Tejas' product and no other way for it to generate revenue. As a practical matter, it was out of business.

Within 12 hours of the Governor's signature on S.B. 178, suit was filed in the District Court of Travis County. Informal negotiations aimed at obtaining TNRCC's agreement that Tejas would not be declared in default under its contracts for failure to reopen after the 90-day suspension (at a time when S.B. 178 reduced demand to zero) were unsuccessful. The State would not even agree that Tejas was relieved of the obligation to keep open 65 locations that were expensive to operate, but for which there was now no demand. A restraining order was sought and obtained. Pertinent excerpts from the Emissions Testing Contracts are in the Appendix. As § 3.12 indicates, Tejas was obliged to present its money damage claim in the first instance to the TNRCC. It served out the appropriate notice letters on May 1, 1995. It submitted a detailed $187 million dollar claim in August 1995 and the TNRCC rejected that claim in its entirety on October 23, 1995. On August 31, 1995, Tejas obtained a fairly well publicized temporary injunction enjoining the State's efforts to call the $8.8 million loan two years early. This was Tejas' first opportunity to submit the impact of S.B. 178 on it to a Judge. The outcome of the temporary injunction hearing supported Tejas' firmly held view that it was treated not only unfairly, but in a manner that could be redressed by the courts, notwithstanding a sovereign immunity argument.

On September 12, 1995, the Tejas companies were forced to file Chapter 11 bankruptcy. Their only source of revenue had been legislated away. In November 1995, an actual money damages lawsuit was filed in the District Court of Travis County. It was that second case filed for money damages that was ultimately tried in January 1997. The second lawsuit was necessary because the immunity waiver statutes from the Texas Health and Safety and Texas Water Codes upon which Tejas relied required "filing suit" within 30 days of TNRCC's decision. Immunity waiver statutes are strictly construed. Accordingly, amending the earlier filed lawsuit for an injunction was just too risky.

By the end of 1995, Tejas had sought and obtained two injunctions to maintain the status quo, had pursued its contractual administrative remedies with the TNRCC unsuccessfully, and had filed suit for breach of contract, for impairment, and for takings. Negotiations aimed at finding a role for the Tejas Testing network in a new State program proved unsuccessful. By early 1996, Tejas had lost the wherewithal to keep its network in place and had only one asset--its lawsuit against the State of Texas and its agencies.

Tejas' goal for 1996 was simple and straightforward. It wanted to get over the sovereign immunity hurdle and obtain a trial court judgment (somewhere) before the legislature returned in January 1997. Failing that, it certainly wished to have the matter resolved through the trial court level before the legislature recessed sine die on June 2, 1997. It anticipated (correctly) two aspects of the State's defense strategy. The State obviously much preferred state court to federal, viewed sovereign immunity and the Legislature's perceived discretion not to pay a judgment as its primary defenses, did not really dispute that it had failed to perform the emissions testing contracts, and really did not relish the outcome of a trial on the merits.

III. THE REMOVAL TO FEDERAL COURT, ELEVENTH AMENDMENT IMMUNITY, AND THE FEDERAL CLAIMS FOR AN INJUNCTION

An affiliate of Snap-On Incorporated ("Snap-On"), a New York Stock Exchange company, had owned Tejas' parent company until July 1994. After the company's LBO sale, Snap-On stayed on as a guarantor of Tejas' $100 million plus construction debt. As a $100 million creditor, it felt it had some interest in a positive outcome of Tejas' claim. It manifested that interest by intervening in the earlier filed state court injunction lawsuit and by removing it to the bankruptcy court in December 1995. The case was later transferred to federal district court when the bankruptcy "reference" was withdrawn. Apparently, implicit in this action was the notion that the tougher sovereign immunity hurdles in federal court were more than offset (in Snap-On's view) by the better developed collection line of cases. It then fell primarily to Tejas to maintain federal jurisdiction over one of its two lawsuits against the state entities. This led to some very interesting litigation pursuant to § 106(b) of the Bankruptcy Code.

To make a long story short, Tejas convinced a United States District Judge that a letter from the State to Tejas reminding Tejas that it still owed the State $8.8 million amounted to a "informal proof of claim" stripping the State of its 11th Amendment and sovereign immunity. The Court's opinion was based in large measure on an unpublished North Carolina case styled Department of Transportation v. AerAerotron. The State of Texas parties appealed the ruling to the Fifth Circuit, and the Tejas/State settlement prevented Fifth Circuit resolution of the matter.(5) In addition to obtaining this ruling that the State had waived its immunity from money damage claims in federal court, Tejas pursued in the federal court claims for declaratory and injunctive relief aimed at enjoining the State's new emissions testing program. There, Tejas argued that S.B. 19 and S.B. 178 violated the Federal Constitution's contract and takings clause, along with various other federal claims. The Federal District Court overruled the State's motion to dismiss on immunity grounds and the State took a second interlocutory appeal to challenge that ruling.(6) All told, the State attempted to stay the federal court trial at least six times before successfully doing so on December 20, 1996. Undeterred, Tejas announced ready for trial in state court on January 13, 1997.

IV. THE STATE COURT TRIAL AND JUDGMENT

On January 15, 1997 (after a two-day ice storm delay), all parties announced ready for trial before The Honorable Joseph H. Hart. Earlier in January, Judge Hart had orally communicated to the parties that he did not find the State's summary judgment motion based on sovereign immunity persuasive.(7) For a case that ended in a $208 million judgment, the trial was amazingly straight forward. Although testimony proceeded over two trial weeks, a construction of no more than three provisions of the emissions testing contract were at the root of the decision. Section 9.3 of the emissions testing contract (excerpts of both §§ 9.3 and 9.5 are included in the Appendix) was the "no fault" termination provision of the contracts. It could be invoked by the TNRCC only if "the [emissions testing] Program is repealed or substantially amended." (emphasis supplied) Tejas argued and Judge Hart agreed that Program is a defined term and related to the State's implementation plan ("SIP") on file with the EPA. It was undisputed that the State had not, before it stopped performing the Tejas contract, jumped through the administrative law hoops necessary to repeal or substantially amend the SIP on file with the EPA. Had the facts supported a more proper § 9.3 invocation, the argument that TNRCC's obligation to Tejas would have been to do no more than ask the legislature for money might have been more persuasive. Judge Hart determined that § 9.5 rather than 9.3 of the contract governed. Section 9.5 (entitled Termination Based on TRNCC's default) provides that "payment by the TACB [now the TNRCC] to the managing contractor of the amount set forth in § 9.3 will constitute full satisfaction of all claims of the managing contractor arising from the default." (emphasis supplied) Judge Hart concluded the TNRCC had breached the contract in at least the following particulars:

  1. Since January 1, 1995, the TNRCC has failed to insure that "all cars shall be tested at Tejas' facilities, in violation of § 4.4 of the Contracts.

  2. Since January 1, 1995, the Defendants have failed to condition vehicle registration on presentment of a vehicle emissions certificate obtained from a Tejas facility, in violation of § 10.1 of the Contracts.

  3. The Defendants decided to cease testing prior to final EPA action amending (or deciding not to amend) the State's I/M program, in violation of a § 4.4 of the Contracts.

  4. The TNRCC failed to fix Tejas' damages in September 1995, in violation of § 3.12 of the Contracts, thus proximately causing Tejas' inability to maintain control of its testing network.

  5. The TRNCC failed to mediate this dispute as required by § 3.12 of the Contracts.

  6. The TNRCC failed to pay all sums owed pursuant to § 9.5 of the Contracts.

  7. The TNRCC requested an amount from the Legislature obviously less than that contemplated by § 9.3.

Based on these conclusions, he held that § 9.5 governed and that a money judgment could be issued rather than just a court directive that the TNRCC ask the legislature for an appropriation. Judge Hart further concluded that Senate Bill 178's language, including but not limited to the language actually rendering illegal the very technology Tejas was contracted to provide, amounted to impairments of contract, a retroactive law, and an unconstitutional taking. Judge Hart's Letter Opinion is included in the Appendix. Judge Hart awarded to Tejas actual damages in the amount of $139,869,441, prejudgment interest totaling $28,724,000, for a total of $168,593,441. Judge Hart also awarded Tejas $40 million in attorney's fees for a total of $208,593,441. Pursuant to contingency fee agreements, Tejas had contracted to pay the Minton firm about $3.2 million and the Bickerstaff firm $10 million at these levels of recovery. However, Tejas' uncontradicted attorneys fees proof at trial (fully compliant with the Texas Supreme Court's then one week old decision in Arthur Andersen & Co. v. Perry Equipment Corp., 945 S.W.2d 812 (Tex. 1997)) fixed the usual, reasonable, and customary fee at $40 million. Court awarded offsets reduced the judgment to about $179,000,000. Judge Hart also authorized Tejas to petition the Texas Legislature for a return on its investment valued by the Court at $53,864,000. Tejas' Operating Contractors ("OCs") were awarded $16.7 million in damages and over $7 million in attorneys' fees.(8)

V. POST-TRIAL MATTERS--HANDSHAKE SETTLEMENT AND THE PASSAGE OF H.B. 1898

After Judge Hart issued his letter opinion on April 4, 1997, but before he even signed a Final Judgment consistent therewith on April 21, settlement discussions began in earnest. By May 18, a handshake deal was made--the State would pay $140 million (with no offsets) in five installments with 10% interest on unpaid amounts. In other words, the State was agreeing to pay 93 cents on the dollar if one reduced the legal fees from the awarded $40 million to the contracted for $13.2 million. Assuming the full $40 million awarded, Tejas was receiving about 85 cents on the dollar. Bankruptcy proof indicated such would be enough to pay Tejas' creditors and investors in full. On May 28, the Texas House (after lively debate) passed H.B. 1898, appropriating around $115 million, enough to fund the first three yearly payments. Payments four and five carry over to the next biennial budget period. The Legislative Budget Board ("LBB") and TNRCC will include those sums in the next biennium's base budget. Tejas and its creditors testified in the Bankruptcy Court that they believe fully in the honor of the TNRCC and the Legislature regarding payments four and five and believe the last installments will be paid. If they are not, established Bankruptcy precedent holds that the damages will revert to the uncompromised amounts.

VI. BEFORE A SETTLEMENT AGREEMENT IS SIGNED, THE SUPREME COURT DECIDES FEDERAL SIGN ON JUNE 20, 1997

The settlement agreement between Tejas and the State was not signed until July 22, 1997 and not funded until Friday, February 13, 1998.(9) The lag from handshake to signing was required so that the State could come to terms with Tejas on certain nonmonetary aspects of the settlement. The July to February lag was required so that the Tejas Bankruptcy Court (and various appellate courts) could pass on the settlement's wisdom pursuant to Bankruptcy Rule 9019.

The Supreme Court's June 20, 1997 opinion in Federal Sign v. Texas Southern University, 951 S.W.2d 401 (Tex. 1997) bore on the two issues with which Tejas had been grappling since December 1994--could it uphold a Judgment against the State through the appeal process and if so, could it then collect that Judgment? As to Tejas (reading between the lines and as a strongly biased advocate), the Supreme Court answered the first question yes and the second question probably/maybe. Federal Sign was a 2-4-3 decision. Justice Baker wrote for a six judge majority joined by Chief Justice Phillips and Justices Gonzalez, Hecht, Cornyn, and Owen. Four of those six (Hecht, Phillips, Cornyn, and Owen) wrote or joined in a Hecht concurrence including vastly limiting language. Three Justices (Enoch, Spector, and Abbott) dissented and were fully prepared to scrap contractual sovereign immunity now. We characterized the opinion then (and now) as 2-4-3 because only Justices Baker and Gonzales were in the majority, but did not join the four concurring Justices in limiting and explaining the holding. The two Justice "majority" handed down precisely the opinion for which Tejas had been planning for 31 months; namely, in a straight contract case, Legislative waiver of immunity from suit must exist even though the mere act of contracting waives immunity from liability. From the May 1995 petition filed just 12 hours after S.B. 178 passed, we were prepared for this holding. Our client had entered into a government contract, the government breached the contract, and we had three state statutes (along with our constitutional claims) authorizing suit. The two member "majority" held.

Therefore, when the State contracts with private citizens, the State waives immunity from liability. However, a private citizen must have legislative consent to sue the State on a breach of contract claim. The act of contracting does not waive the State's immunity from suit. Accordingly, we expressly overrule any cases that hold to the contrary."

951 S.W.2d at 408.

Even these two Justices stated in the text and in a footnote that their opinion was narrow. In reciting the facts of the case, the majority stressed that Federal Sign had prepared to perform but had tendered no performance. That recitation gave a fully performing contractor like Tejas great relief.

The four member concurrence went further:

[A]t the time of TSU's breach (as found by the jury), Federal Sign had not performed. To be sure, Federal Sign purchased equipment for the contract that it could not otherwise use and lost profits it had bargained for. But Federal Sign never tendered performance, never performed services on T's property, and never delivered TSU any materials. Would the result be different if Federal Sign had already installed the scoreboards and TSU refused to pay the agreed price? Or if TSU refused to pay in order to force Federal Sign to make a concession on another contract? We do not attempt to decide such hypotheticals today, but they do suggest that the State may waive immunity by conduct other than simply executing a contract, so that it is not always immune from contract suits.(10)

951 S.W.2d 412 (emphasis supplied).

On appeal, Tejas would have pointed to its status as an acknowledged, fully performing and horribly treated, contractor and asked the four concurrers, three dissenters, and even the two member "majority" to answer the reserved question in Tejas' favor. Tejas would have argued it was the perfect "waiver by conduct" Plaintiff. Now, we will never know if Tejas would have been successful in that argument.

Just as the concurrence gave contract claimants some hope of obtaining a Judgment, the concurrence was not so generous in terms of collecting nonconstitutional claims,

a waiver of immunity would not provide the full redress the dissent contends is essential for a contract with the State to be enforceable. Even if the State is held liable in a suit for breach of contract, it cannot be forced to pay the judgment. The Legislature may simply refuse to appropriate the funds. There is no reason why requiring legislative consent to sue makes a contract unenforceable but requiring legislative consent to collect does not.

951 S.W.2d 415 (emphasis supplied).

Of course, Tejas would have argued that the impairment and takings underpinnings of its Judgment created a situation in which the Legislature could not constitutionally refuse to appropriate funds necessary to satisfy its Judgment after all appeals had been exhausted.(11)

VII. CONCLUSION

It was a wild and unforgettable ride. Undecided at this time is whether the Courts and the Legislature will soon express that the State of Texas is a contracting party on whom individuals and businesses may confidently rely. We hope they will and think they should.

FOOTNOTES

1. This section is summarized, shortened, slightly fictionalized, does not represent an actual conversation and is not intended to waive the attorney/client privilege. No references to our work and thought processes are intended to be a waver of any kind.

2. Alcorn v. Vaksman, 877 S.W.2d 390, 403 (Tex. App.--Houston [1st Dist.] 1994, writ denied); Green Int'l, Inc. v. State, 877 S.W.2d 428, 432-33 (Tex.App.--Austin 1994, writ dism'd); Atchison, Topeka & Santa Fe Ry. v. Texas State Dep't of Highways and Pub. Transp., 783 S.W.2d 646, 648 (Tex.App.--Houston [14th Dist] 1989, no writ); Texas Dep't of Human Servs. v. Trinity Coalition, Inc., 759 S.W.2d 762, 764 (Tex.App.--El Paso 1988, writ dism'd w.o.j.) cert. denied, 493 U.S. 1020, 110 S.Ct. 719, 107 L.Ed.2d 739 (1990); Miller v. Hood, 536 S.W.2d 278, 284 (Tex.Civ.App.--Corpus Christi 1976, writ ref'd n.r.e.).

3. NTREH v. University of Texas at Dallas, 936 S.W.2d 649, 654 (Tex.App.--Dallas 1996), modified, 947 S.W.2d 202 (Tex. 1997); Texas Dept. Of Health v. Texas Health Ent., 871 S.W.2d 498, 506 (Tex.App.--Dallas 1993, writ denied); Couch v. Ector County, 860 S.W.2d 659, 661 (Tex.App.--El Paso 1993, no writ); Industrial Constr. Management v. DeSoto Indep. Sch. Dist., 785 S.W.2d 160, 163-164 (Tex.App.--Dallas 1989, no writ); Board of Regents of Univ. Of Texas v. S & G Constr. Co, 529 S.W.2d 90, 97 (Tex.Civ.App.--Austin 1975, writ ref'd n.r.e.); Cummins v. Board of Trustees of Eanes Indep. Sch. Dist., 468 S.W.2d 913, 917 (Tex.Civ.App.--Austin 1971, no writ).

4. Substituting descriptions like Ground Hog's Day and Valentine's Day for dates is a concept shamelessly, but respectfully, stolen from Senior United States District Judge Lucius D. Bunton.

5. Whether Tejas could have successfully defended its 106(b) waiver argument and proceeded against the State for contract money damages in federal court is a very interesting question. In May, 1998 the Fifth Circuit (through Judge Edith H. Jones) wrote State of Texas By and Through Bd. of Regents of Univ. of Tex. System v. Walker, 142 F.3d 813 (5th Cir. 1998). There, Judge Jones embraced the case at the center of Tejas 106(b) waiver argument, Gardner v. State of New Jersey, 329 U.S. 565, 67 S.Ct. 467 (1947). Gardner holds, "It is traditional bankruptcy law that he who invokes the aid of the bankruptcy court by offering a proof of claim and demanding its allowance must abide the consequences of that procedure." 329 U.S. at 573. On July 22, 1998, the Eleventh Circuit flat out held that (on federal common law grounds) a State waives sovereign immunity when it files a proof of claim. In Re: Burke, 146 F.3d 1313 (11th Cir. 1998) However, other Courts have ruled differently. The Fourth Circuit reversed Aerotron and a bankruptcy court in Virginia struck § 106(b) as unconstitutional. In re NVR L.P., 206 B.R. 831 (Bankr. E.D. Va. 1997), aff'd sub nom. Clerk of Circuit Court for Anne Arundel County v. NVR Homes, Inc., 222 B.R. 514 (E.D. Va. Jul. 17, 1998). The Eleventh Circuit, by stressing federal common law, avoided passing on the validity of § 106(b). Perhaps the Fourth/Eleventh Circuit conflict will be resolved; perhaps not.

6. On June 26, 1998, Tejas' theory that attempting to enjoin the State's new emissions testing program properly invoked the subject matter jurisdiction of the federal court was vindicated. In the unsettled dispute between the Operating Contractors and the State parties, the Fifth Circuit affirmed the notion that declaratory and injunctive relief could be awarded to Tejas or its Operating Contractors in federal court. The Operating Contractors' injunction claims are set for trial on the merits on November 3, 1998.

7. Judge Hart later wrote that he viewed all three statutes cited by Tejas as waivers of immunity from suit and agreed with Tejas' argument that its constitutional arguments relating particularly to impairment and taking trumped the sovereign immunity doctrine.

8. The OCs did not settle with the State. The State's appeal of that $23 million judgment has been fully briefed in the Austin Court. As mentioned above, the OC versus State federal injunction claim is set for trial November 3, 1998.

9. Funding on Friday the Thirteenth motivates Tejas (or at least its trial lawyers) to believe that Friday the Thirteenth has been set back perhaps irretrievably as an unlucky day. Many of the Bankruptcy aspects of the Tejas experience are beyond the scope of this paper. However, it should come as no surprise that if the government breaches a contract with a company whose only business is that government contract, said company will likely take Bankruptcy. Bankruptcies are usually a separate struggle between Owners and various classes of Creditors over the available money.

10. Subsequent citations to Federal Sign through August 26, 1998 (the date this article went to press) shed no light as to whether "waiver of immunity by conduct" will take hold as a theory.

11. Again, we will never know whether the Legislature would have ignored or failed to fund fully a final breach of contract, takings, and impairment judgment in such a large amount with such aggravated facts.


Email Us Publications
 Return to Main

Copyright © 1996-1998 State Bar of Texas Administrative and Public Law Section, All Rights Reserved.